1.1.................... moves to amend H.F. No. 1097, the delete everything amendment
1.2(H1097DE1-2), as follows:
1.3Page 44, after line 22, insert:
1.4 "Sec. 83.
[116C.10] ENVIRONMENTAL PERMIT TIMELINE REQUIREMENT.
1.5If environmental review under chapter 116D is or will be conducted for a project
1.6and a state agency is the responsible government unit, the state agency named as the
1.7responsible government unit shall develop a timeline for all state agency environmental
1.8permits required for the project and make that timeline available to the project proposer,
1.9within 30 days after complete applications have been submitted for all permits, or by the
1.10time of environmental assessment worksheet or draft environmental impact statement
1.11publication. If joint state-federal environmental review is being conducted, the timeline
1.12shall also include required federal agency environmental permits."
1.13Page 47, line 18, strike "25" and insert "
100"
1.14Page 47, line 19, after "individuals" insert "
who reside or own property in the county
1.15or an adjoining county where the proposed action will be located"
1.16Renumber the sections in sequence and correct the internal references
1.17Amend the title accordingly